Link copied to clipboard
Case Study — Industry Twin Lab
Case Study 7 April 2025 13 min read

Simulating an Entire Factory Floor Before a Single Machine Moves — Industry Twin Lab in Action.

How our Industry Twin Lab environment let an industrial client stress-test layout changes, automation sequences, and failure scenarios entirely in simulation — eliminating weeks of physical trial and error.

Botron Dynamics Engineering Digital Twins & Simulation Team

Key takeaways

  • A high-fidelity factory digital twin built before physical reconfiguration begins can identify bottlenecks, collision risks, and throughput losses that no static planning tool can surface.
  • Automation sequence validation in simulation is categorically different from vendor acceptance testing — it tests the interaction between systems, not each system in isolation.
  • Failure scenario injection — simulating conveyor faults, robot arm stoppages, and supply interruptions under live production load — reveals cascade failure modes invisible in normal operation.
  • The return on simulation investment compounds: the same twin used for pre-commissioning layout validation continues as an operational tool for change management, training, and predictive maintenance modelling.

The challenge: reconfiguring a live factory without stopping it

Industrial reconfiguration projects carry a cost that rarely appears on the project plan: the cost of being wrong. Moving a production line, introducing a new robotic cell, or changing the sequencing of an automated assembly process are decisions that, once committed to in the physical world, are expensive to reverse. Equipment is bolted down, conveyors are cut to length, and PLC logic is written to the new layout. When a problem emerges — a bottleneck that wasn't visible in the CAD model, a collision envelope that two robots share at an unlikely but real moment in their cycles, a throughput loss that only materialises under shift-change load patterns — the factory is already rebuilt around it.

The client in this engagement operated a mid-scale precision components manufacturing facility running two shifts, with a planned expansion that would introduce three new automated assembly cells, a reconfigured inbound materials flow, and a revised finished-goods dispatch sequence. The programme had a fixed go-live window driven by a contracted delivery commitment. There was no margin for a physical trial-and-error phase. The question was not whether to simulate — it was whether the simulation could be made authoritative enough to trust.

"Moving equipment and discovering a problem costs weeks. Discovering the same problem in simulation costs an afternoon."

The Industry Twin Lab engagement

Industry Twin Lab is Botron Dynamics' structured environment for building, validating, and operating high-fidelity digital twins of industrial facilities. The engagement for this client began eight weeks before the physical reconfiguration was scheduled to start, with an initial phase of facility data acquisition: laser scanning of the existing floor, extraction of equipment geometry and kinematics from vendor specifications, ingestion of production scheduling data, and instrumentation of key throughput and cycle-time metrics from the existing SCADA and MES systems.

The resulting twin modelled the factory at component level — individual conveyor segments, robot arm articulation ranges, AGV routing logic, buffer station capacities, and operator workstation positions — and was driven by a production schedule engine that replicated the actual shift patterns, batch sizes, and product mix the facility runs. The twin was not a visualisation. It was a physics-aware, schedule-driven simulation capable of running faster than real time for scenario exploration and at real-time fidelity for operator training and commissioning rehearsal.

6
Critical bottlenecks and collision risks identified and resolved entirely in simulation before physical work began
23 days
Estimated physical trial-and-error time eliminated by pre-commissioning simulation validation
99.2%
Throughput prediction accuracy of the twin versus actual post-commissioning production metrics

Layout validation: finding what CAD cannot show

The client's engineering team had produced a detailed CAD layout of the reconfigured floor. It was geometrically correct — every machine footprint, aisle width, and service access zone was accurately represented. What it could not show was the facility in motion. Static CAD models have no concept of a robot arm at full extension during a pick cycle, an AGV taking a cornering path under load, or a forklift route that is safe at normal staffing levels and dangerous when a second forklift is added during a shift changeover.

Loading the CAD geometry into the Industry Twin Lab environment and running the production schedule against it revealed three issues within the first simulation cycle that the static layout had not flagged. A robot arm in the new Cell 3 had a collision envelope overlap with a conveyor transfer point that only occurred during one specific product variant's pick sequence — a variant that ran approximately twice per shift. An AGV routing path that appeared clear in the static layout became a conflict point when two AGVs converged on the same node under the peak-load scheduling pattern. And the buffer station between the new inbound flow and the first assembly cell was sized correctly for average throughput but undersized for the burst pattern that occurred at the start of each shift when the previous shift's queue cleared simultaneously.

Why dynamic simulation finds what static layout review misses

Static layout review checks geometry. Dynamic simulation checks behaviour. The collision that occurs at one moment in a robot's seven-second cycle, the buffer that empties at exactly the wrong time, the AGV path that works at four vehicles and fails at five — none of these are findable by looking at a floor plan. They only appear when the facility is running, which in a physical setting means they appear after commissioning. In simulation, they appear before a single bolt is turned.

Automation sequence validation across integrated systems

Vendor acceptance testing for industrial automation equipment validates that each system performs its specified function in isolation. The robot arm reaches its target position within tolerance. The conveyor runs at its rated speed. The vision system classifies the test part correctly. What acceptance testing cannot validate is the interaction between systems when they are integrated and running under a real production schedule — because at acceptance testing time, the other systems are not present.

The Industry Twin Lab environment models automation systems at the PLC logic level, allowing the client's engineering team to connect the actual control logic — or high-fidelity emulations of it — to the simulated physical environment. This means the integration between systems is tested in simulation before it is tested in the physical facility. Handoff timing between conveyor segments and robot pick cycles, interlock logic between adjacent cells, and the sequencing of the dispatch buffer release against the finished-goods scanning station were all validated against the full production schedule in simulation before the physical systems were installed.

Validation type What it tests When it can be done in simulation Risk if deferred to physical commissioning
Layout validation Collision envelopes, aisle clearances, AGV routing conflicts, and buffer sizing under real production load patterns. As soon as equipment geometry and production schedules are available — before physical installation begins. Equipment repositioning after installation typically costs 3–10× the cost of the original installation move.
Automation sequence validation Handoff timing, interlock logic, and cross-cell sequencing under integrated production conditions. Once PLC logic or control emulations are available, before physical integration wiring is complete. Integration faults found during physical commissioning stop the entire line, not just the affected cell.
Failure scenario testing Cascade failure modes, recovery sequence correctness, and operator response time requirements under injected fault conditions. At any point once the twin is running — and repeatably, without production impact. Cascade failures in a live facility cause unplanned downtime; some failure modes cannot be safely induced physically at all.

The sequence validation phase identified two interlock logic errors that would have caused cell stoppages under specific but non-rare production conditions: one in the handoff timing between Cell 2's output conveyor and the shared transfer buffer, and one in the interlock that governed Cell 3's entry gate relative to the AGV docking position. Both were resolved in the control logic before the physical systems were installed. Neither would have been visible in vendor acceptance testing, because they only manifested when both systems were running simultaneously under load.

Failure scenario injection and cascade analysis

A factory digital twin that only models normal operation is a planning tool. A twin that can simulate failure is a resilience tool. The Industry Twin Lab environment includes a fault injection framework that allows specific failure modes to be introduced into the running simulation — a conveyor segment stopping mid-cycle, a robot arm entering a fault state, a vision system dropping classification confidence below threshold, a supply pallet arriving out of sequence — and the cascade effects to be observed, measured, and recorded across the full facility model.

For this engagement, the failure scenario suite covered seventeen distinct fault types drawn from the client's historical downtime records and a structured FMEA conducted during the twin build phase. Each fault was injected at multiple points in the production schedule — at shift start, at peak load, and during shift changeover — to identify whether cascade severity varied with production state. In eleven of the seventeen cases, the cascade profile was significantly worse at one scheduling point than others, a result that drove changes to the recovery procedure documentation and operator training scenarios.

The cascade failure modes that cannot be found any other way

Some failure modes cannot be safely induced in a live production environment. A conveyor stoppage that, under the right conditions, causes a queue backup that triggers a second stoppage upstream, which in turn causes an AGV routing deadlock — this is not a scenario an engineering team can deliberately create in a running factory to observe and document. In simulation, it can be induced, observed at any playback speed, rewound, and re-run with a modified recovery sequence to verify the fix. The twin does not just find the problem; it provides the environment to validate the solution before anyone acts on it in the physical facility.

Pre-commissioning rehearsal and operator training

The final phase of the Industry Twin Lab engagement used the validated twin as a commissioning rehearsal environment. The client's engineering and operations teams ran the new cell start-up sequence against the simulation before running it against the physical facility — identifying the correct order of operations, the hold points that required operator confirmation, and the monitoring parameters that needed to be watched during the first live production run. Operators who would be responsible for the new cells during normal production used the twin for familiarisation and fault-response training in the weeks before go-live.

The commissioning rehearsal identified one sequencing assumption in the start-up procedure that was incorrect — the physical interlock for Cell 3's safety guarding required a confirmation step that the draft procedure had placed after a step that would have triggered a fault. Discovered in simulation during rehearsal, the fix was a two-line procedure change. Discovered during physical commissioning, it would have been a stopped line and an unplanned investigation.

"The twin is not retired at go-live. It becomes the change management environment for every layout, process, or scheduling modification that follows."

Results at and after go-live

The physical reconfiguration and commissioning of the expanded facility completed within the contracted go-live window — the first time in the client's recent capital programme history that a reconfiguration of this scale had not required a schedule extension. Post-commissioning throughput on the new assembly cells matched the twin's predictions to within 0.8% at steady-state production, validating the fidelity of the simulation model against physical reality.

The six issues identified and resolved in simulation — three layout conflicts, two interlock logic errors, and one commissioning procedure sequencing fault — were each estimated by the client's engineering team to have required between two and six days of physical investigation and rectification had they been discovered after go-live. The combined avoidance of those rectification periods, plus the elimination of the planned physical trial-and-error phase that had originally been budgeted at three weeks, represented the primary measurable return on the simulation engagement.

Six months post-commissioning, the Industry Twin Lab twin remains live and connected to the facility's production data feeds. It has since been used to evaluate a proposed shift pattern change, to model the impact of a new product variant on Cell 2 throughput, and to pre-validate a minor conveyor layout adjustment requested by the operations team. The twin does not expire at go-live; it becomes the ongoing change management environment for the facility.

What this demonstrates

The value of a factory digital twin is not the visualisation — it is the ability to run a facility that does not yet exist, or a change that has not yet been made, against real production conditions, and to discover problems before they are embedded in steel and concrete. Industry Twin Lab is built on the principle that simulation fidelity must be high enough to trust: not a schematic approximation of the floor, but a physics-aware, schedule-driven model of the specific facility, running the specific production logic, validated against real operational data before it is used to make real decisions.

The principles demonstrated here — pre-commissioning layout validation, integrated automation sequence testing, failure scenario injection, and commissioning rehearsal — are applicable across facility scales and industry sectors. The investment in building a twin of sufficient fidelity is front-loaded; the returns compound across the full operational life of the facility it models.

Digital Twins Factory Simulation Industry Twin Lab Industrial Automation Simulation Manufacturing
Share

Work with us

Have a problem that needs
prediction, vision,
or simulation?

Talk to our engineering team about what we can build for your platform — from autonomous systems and space technology to enterprise AI pipelines.

Get in touch

Start a conversation with our engineering team

Talk to our team Learn about us

Typically respond within one business day